Foundation works for apartment blocks F1 and F2, adjacent to Foxtree Court and Maple Court to commence at the beginning of October 2018

Enabling works to these plots have been completed.
Main construction works will commence on the 11th March 2019.
Piling and foundation works will begin with block G and then progress to block F2 and finally block F1. This will take approximately 9 weeks to complete.

Works are progressing as planned for the block F2 car park.
It is planned that the car park will be handed over for use by the residents in mid March 2019.

Completion of new shops and apartment blocks E2, E3, F1, F2 and G by March 2020